Question: The following activity network table is given. Activity Duration (days) Predecessor Resource A 4 -- Employee 1 B 10 A Employee 2 C 5 A

The following activity network table is given.

Activity

Duration (days)

Predecessor

Resource

A

4

--

Employee 1

B

10

A

Employee 2

C

5

A

Employee 3

D

6

B, C

Employee 4

E

5

D

Employee 5

  1. Construct a Gantt chart for this project.

The following activity network table is given.

B. Assume that (i) each employee has been assigned to the project activity on a full-time (8 hours/day or 40 hours/week) basis; (ii) On Day 3, Day 11, and Day 18, no employees are allowed to work; (iii) On Day 6, either Employee 2 or Employee 3 can work; and (iv) On Day 12, Employee 2 has a day off. (No video is available for this part of the question; you need to think! If the project starts on Day 1, project will be completed on day (Hint: Earliest day to complete the project) 1 2 3 4 5 6 7 89 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Activity/Day A B D E C. Assume that (i) each employee has been assigned to the project activity on a full-time (8 hours/day or 40 hours/week) basis; (ii) On Day 3, Day 11, and Day 18, no employees are allowed to work; (iii) On Day 6, either Employee 2 or Employee 3 can work; and (iv) On Day 12, Employee 2 has a day off. (No video is available for this part of the question; you need to think! ) If the project starts on Day 2, project will be completed on day (Hint: Earliest day to complete the project) 1 2 3 4 5 6 7 8 9 10 11 12. 13 14 15 16 17 18 19 20 21 22 23 | 24 25 26 27 28 29 30 Activity/Day A B D E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!