Question: The following activity network table is given. Activity Duration (days) Predecessor Resource A 4 -- Employee 1 B 10 A Employee 2 C 5 A
The following activity network table is given.
| Activity | Duration (days) | Predecessor | Resource |
| A | 4 | -- | Employee 1 |
| B | 10 | A | Employee 2 |
| C | 5 | A | Employee 3 |
| D | 6 | B, C | Employee 4 |
| E | 5 | D | Employee 5 |
- Construct a Gantt chart for this project.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
