Question: The following activity network table is given for Project Why? Assume that (i) each employee has been assigned to the project activity on a full-time

The following activity network table is given for Project Why? Assume that (i) each employee has been assigned to the project activity on a full-time ( 8 hours/day or 40 hours/week) basis; (ii) On Day 3 , Day 11 , and Day 18 , no employees are allowed to work; (iii) On Day 6 , either Employee 2 or Employee 3 can work; and (iv) On Day 12, Employee 2 has a day off. Question \#3 If the project starts on Day 1 , project will be completed on Day Hint: Find the earliest day to complete the project. No video is available for this part of the question; you need to think! A. 21 B. 22 C. 23 D. 24 E. 25 F. 26 G. 27 H. 28 I. 29 J. 30 K. 31 L. Cannot be determined using the given information. M. None of the above