Question: The following are duration estimates for a project: CRITICAL PATH TASKS TASK O M P E V A 1 3 5 3 0.44 B 2
The following are duration estimates for a project: CRITICAL PATH TASKS TASK O M P E V A 1 3 5 3 0.44 B 2 4 6 E 1 2 6 2.5 0.69 F 1 3 7 H 1 2 3 2 0.11 TOTAL OTHER PROJECT TASKS TASK O M P E V C 0.5 1 3 1.25 0.17 D 1 2 3 2 0.11 G 0.5 1 6 1.75 0.84 TOTAL What is the Z value is we are interested in finding the probability that the project lasts less than 15.5 days? Give your answers to 3 decimal places