Question: The following data is provided for a PPP project. To the People To the Government Benefits $90,000 per year beginning now Cost $1.8 million now
The following data is provided for a PPP project.
| To the People | To the Government | ||
| Benefits | $90,000 per year beginning now | Cost | $1.8 million now and $200,000 every 3 years |
| Disbenefits | $30,000 per year | Savings | $120,000 per year |
Calculate the modified benefit/cost ratios using an interest rate of 9% per year and an infinite project period.
The modified B/C ratio is ( )