Question: ! Required information The following data is provided for a PPP project. To the People To the Government $1.8 million now and $200,000 Benefits $85,000

! Required information The following data is provided for a PPP project. To the People To the Government $1.8 million now and $200,000 Benefits $85,000 per year beginning now Cost 3 years Disbenefits $20,000 per year Savings $100,000 per year Calculate the conventional benefit/cost ratios using an interest rate of 11% per year and an infinite project period. The conventional B/C ratio is