Question: The following information has been given for your consideration a Estimated Factory Overhead for the next period P 500,000 b Estimated UNITS to be
The following information has been given for your consideration a Estimated Factory Overhead for the next period P 500,000 b Estimated UNITS to be produced u 10,000 c Materials cost for the units to be produced P 400,000 d Direct labor hours required to produce the units hrs 25,000 e Direct labor COST required to produce the units P 250,000 f Machine hours to be used hrs 80,000 Required: Compute the PRE-DETERMINED FACTORY OVERHEAD RATE BASED ON... 1 Material cost 2 Units of production 3 Machine hours 4 Direct Labor hours 5 Direct Labor cost
Step by Step Solution
3.40 Rating (156 Votes )
There are 3 Steps involved in it
The predetermined factory overhead rate is calculated by dividing the estimated factory overhead costs by a chosen cost driver In this case you are gi... View full answer