Question: The following information is available. Determine the variable overhead spending variance. Direct labor standard (2 hrs. @ $12.75/hr.)$25.50per finished unit Actual direct labor hours81,500hrs. Budgeted
The following information is available. Determine the variable overhead spending variance.
Direct labor standard (2 hrs. @ $12.75/hr.)$25.50per finished unit
Actual direct labor hours81,500hrs.
Budgeted units42,000units
Actual finished units produced40,000units
Standard variable OH rate per hour$14.30
Standard variable OH rate (2 hrs. @ $14.30/hr.)$ 28.60 per hour per finished unit
Standard fixed OH rate ($336,000/42,000 units)$8.00per unit
Actual cost of variable overhead costs incurred$1,140,000
Actual cost of fixed overhead costs incurred$338,000
Step by Step Solution
3.38 Rating (145 Votes )
There are 3 Steps involved in it
To determine the variable overhead ... View full answer