Question: The following information is available for a project in progress: P V = $ 3 0 0 ;BAC = $ 8 0 0 ; E

The following information is available for a project in progress: PV=$300;BAC=$800;EV=$330; and AC=$320. The PCIB for the project is:
0.979
0.412
10
1.10
 The following information is available for a project in progress: PV=$300;BAC=$800;EV=$330;