Question: The following information is given for a construction project to add another small training facility at a retail company ( time in weeks ) :

The following information is given for a construction project to add another small training facility at a retail company (time in weeks):
\table[[Activity,Duration,Predecessor],[a,4,None],[b,6,a],[c,4,a],[d,2,c],[e,4,b],[f,5,b, d],[g,3,c],[h,4,f, g],[i,2,e, h]]
Question 1(5 Points):
What is the critical path?
Question 2(5 Points):
What is the project completion time?
Question 3(5 Points):
What is the sum of all slack times?
Question 4(5 Points):
Create a Gantt chart.
 The following information is given for a construction project to add

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!