Question: The following information is provided for crashing analysis. Task NT CT Normal cost Crash cost Imm . Pred. A 8 6 1 4 0 0

The following information is provided for crashing analysis.
Task NT CTNormal cost Crash cost Imm. Pred.
A8614001600--
B55500500--
C32800850 A
D4311001300 B
E659001150 C,D
The project will take [ Select ]["17","15","18","20"] days to complete.
In what order would you crash the activities to crash the project by 3 days? [ Select ]["ABC", "CAAD", "CAA", "CAE"]
What is the additional cost to do this crashing? [ Select ]["450","400","550","350"]
After crashing, the project will be completed in [ Select ]["14","13","15","16",""] days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!