Question: The following information represents the Work Breakdown Structure (WBS) for the construction steps necessary for HBU to turn the Sky Hall building into classrooms and

The following information represents the Work Breakdown Structure (WBS) for the construction steps necessary for HBU to turn the Sky Hall building into classrooms and offices that can be used in the Fall 2021 semester.

Question #1 --- Map the project and determine the critical path and completion time for the construction project. Based on your answer, will this project be done in time for HBU to use this facility at the beginning of the Fall 2021 semester which starts in 5 months?

ACTIVITY: A------B ----C--- D-----E----F

IP:........ NONE---A-----A---B,C---B---D,C

T(Months): 1-----3-----4-----2 ----2----2

(This was the only way I could aline them)

Ex: A,None,1= first column . B,A,3= second column . C,A,4 third column . ETC.

Please provide evidence of your solution.

Question #2 --- If the variance for the project is 4 months, what is the project time at the 90th percentile, what is the project time at the 30th percentile, and what is the probability that the facility will be ready in 5 months? Please provide evidence of your solution.

Question #3 --- If you have the option to add a great employee, a so-so employee, and a horrible employee.to which activity or activities would you assign each of the additional employees? Why? Please type your answer in the space below.

This is how the questions are given to us

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!