Question: The following information represents the Work Breakdown Structure (WBS) for the construction steps necessary for UIW to turn Founders Hall (the old AT&T Building) into
The following information represents the Work Breakdown Structure (WBS) for the construction steps necessary for UIW to turn Founders Hall (the old AT&T Building) into classrooms and offices that can be used in the Fall 2021 semester.
Question #1 --- Map the project and determine the critical path and completion time for the construction project. Based on your answer, will this project be done in time for UIW to use this facility at the beginning of the Fall 2021 semester which starts in 5 months?
ACTIVITY IP TIME (Months)
A none 1 B A 3
C A 4
D B,C 2
E B 2
F D,C 2