Question: The following operations ( with cycle times ) are needed to release a customer order to production: task 1 : Define Bill of Materials: 2

The following operations (with cycle times) are needed to release a customer order to production:
task 1: Define Bill of Materials: 2 days
task 2a: Order and receive materials (can be done concurrent with 2b): 10 days
task 2b1: Schedule job in production (can be done concurrent with 2a, but must be before 2b2 and 2b3) : 3 day
task 2b2. Define quality plan for product (can be done concurrent with 2a, but must be after 2b1 and before 2b3).1 day
task 2b3 : Enter schedule and quality requirements into scheduling software (can be done concurrent with 2a, but must be after 2b1 and 2b2): 1 day
task 3: Release to production
The total cycle time for the process is:
17 days
12 days
7 days
Cannot be determined with the information provided
 The following operations (with cycle times) are needed to release a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!