Question: The following operations ( with cycle times ) are needed to release a customer order to production: 1 . Define Bill of Materials: 2 days

The following operations (with cycle times) are needed to release a customer order to production:
1. Define Bill of Materials: 2 days
2a. Order and receive materials (can be done concurrent with 2b): 10 days
2b1. Schedule job in production (can be done concurrent with 2a, but must be before 2b2 and 2b3): 3 day
2b2. Define quality plan for product (can be done concurrent with 2a, but must be after 2b1 and before 2b3): 1 day
2b3: Enter schedule and quality requirements into scheduling software (can be done concurrent with 2a, but must be after 2b1 and 2b2): 1 day.
3. Release to production
The latest start time for step 2b2 is:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!