Question: The following partial information is contained in the variance analysis received from the Western Plant of Eastlawn Company. All plants at Eastlawn apply overhead on

The following partial information is contained in the variance analysis received from the Western Plant of Eastlawn Company. All plants at Eastlawn apply overhead on the basis of direct labor-hours.
Flexible budget for variable overhead based on 3,500 direct labor-hours
$ 98,000
Actual total overhead incurred
$ 489,300
Actual direct labor-hours worked
3,562
Direct labor-hours used to determined the fixed overhead application rate
3,250
Price variance for variable overhead
$ 6,450
F
Price variance for fixed overhead
$ 12,514
U
Required:
a.Prepare a fixed overhead analysis.
Price variance
Production volume variance
Fixed overhead total variance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!