The following question(s) use the information in this MRP record. The lead time is 3 weeks. Week 12345
Gross requirements 6050607020
Scheduled receipts 100
Projected available 40903040
Net requirements
Planned order receipt
Planned order release 100
The projected available to be shown in week three is: