Question: The following question ( s ) use the information in this MRP record. The lead time is 3 weeks. Week 1 2 3 4 5
The following questions use the information in this MRP record. The lead time is weeks. Week
Gross requirements
Scheduled receipts
Projected available
Net requirements
Planned order receipt
Planned order release
The projected available to be shown in week three is: