Question: The following question ( s ) use the information in this MRP record. The lead time is 3 weeks. Week 1 2 3 4 5

The following question(s) use the information in this MRP record. The lead time is 3 weeks.
Week 12345
Gross requirements 6050607020
Scheduled receipts 100
Projected available 4090 XX 6040
Net requirements
Planned order receipt 100
Planned order release 100
Based on this MRP record, we can conclude that the beginning on-hand inventory is: