Question: The following represents a project that should b e scheduled using C P M : Use Appendix G . TIMES ( D A Y S

The following represents a project that should be scheduled using CPM: Use Appendix G.
TIMES (DAYS)
ACTIVITY IMMEDIATE
PREDECESSORS amb
A-147
B-1611
CA267
DA2313
EB126
FC,D159
GD,E129
HF,G369
b. What is the critical path?
multiple choice
A-D-F-H
A-D-G-H
A-C-F-H
B-E-G-H
c.
What is the expected project completion time? (Do not round intermediate calculations. Round your answer to3 decimal places.)
Project completion time
20.5
days
d.
What is the probability of completing this project within 23 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to2 decimal places and final answer to4 decimal places.)
Probability
.8810
Please ignore my responses, im still unsure if they are correct

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!