Question: The following represents a project that should b e scheduled using C P M : b . What i s the critical path? B -

The following represents a project that should be scheduled using CPM:
b. What is the critical path?
B-E-G-H
A-D-G-H
A-D-F-H
A-C-F-H
c. What is the expected project completion time?
Note: Do not round Intermedlate calculatlons. Round your answer to3 decimal places.
Project completion time ,19.500 days
d. What is the probability of completing this project within 20 days?
Note: Use Excel's NORM.S.DIST() functlon to find the correct probabllity for your computed Z-value. Do not round Intermedlate
calculations. Round "z" value to2 decimal places and final answer to4 decimal places.
 The following represents a project that should be scheduled using CPM:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!