Question: Given the following task time estimates ( days ) TaskTimePredecessorA 1 9 - - B 1 2 - - C 9 D 1 2 AE
Given the following task time estimates days
TaskTimePredecessorABCDAEB CFD EGDHFIG H
a What is the critical path? Select B C F H I", A C D GA D E F G I", C E F H I", B E F H I"
b What is the project length? Select days", days", days", days", days"
c How much slack in task B Select zero it is on the critical path"
d How much slack is in task A Select days", days", day", days", "zero it is on the critical path"
e What is the early start early finish for task F Select and and and and and
f What is the late start late finish for task G Select and and and and and
g What if task A increased by days. What would be the project length and the critical path? Select days; critical path B E F G H I", days; critical path C F G H I", no change same as the current time frame and critical path", "a reduction to days; critical path C D E G H I", days; critical path A D F G H I"
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock