Question: Given the following task time estimates ( days ) TaskTimePredecessorA 1 9 - - B 1 2 - - C 9 D 1 2 AE

Given the following task time estimates (days)
TaskTimePredecessorA19--B12--C9D12AE20B, CF14D, EG28DH15FI18G, H
a. What is the critical path? [ Select ]["B, C, F, H, I", "A, C, D, G","A, D, E, F, G, I", "C, E, F, H, I", "B, E, F, H, I"]
b. What is the project length? [ Select ]["75 days", "91.5 days", "79 days", "72.5 days", "83 days"]
c. How much slack in task B.?[ Select ]["1","4","2","3","0(zero), it is on the critical path"]
d. How much slack is in task A.?[ Select ]["8 days", "3 days", "1 day", "15 days", "zero - it is on the critical path"]
e. What is the early start / early finish for task F.?[ Select ]["32 and 46","61 and 79","20 and 34","0 and 14","19 and 31"]
f. What is the late start / late finish for task G.?[ Select ]["20 and 32","12 and 32","31 and 59","33 and 61","46 and 61"]
g. What if task A increased by 2 days. What would be the project length and the critical path? [ Select ]["81 days; critical path B, E, F, G, H, I", "82 days; critical path C, F, G, H, I", "no change - same as the current time frame and critical path", "a reduction to 77 days; critical path C, D, E, G, H, I", "80 days; critical path A, D, F, G, H, I"]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!