Question: The following represents a project that should be scheduled using CPM: b. What is the critical path? A.D-G-HB.E-G-HA.D-F-HA.C.F.H c. What is the expected project completion

The following represents a project that should be scheduled using CPM: b. What is the critical path? A.D-G-HB.E-G-HA.D-F-HA.C.F.H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places. b. What is the critical path? A.D-G-H B-E-G-H ADF=H AC=FH c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.) d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round " z " value to 2 decimal places and final answer to 4 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts