Question: The following represents a project that should be scheduled using CPM: Times ( days ) Activity Immediate Predecessors a m b A 1 3 5
The following represents a project that should be scheduled using
CPM:
Times days
Activity Immediate Predecessors a m b
A
B
C A
D A
E B
F C D
G D E
H F G
a Draw the network.
b What is the critical path?
c What is the expected project completion time?
d What is the probability of completing this project within days?