Question: The following represents a project that should be scheduled using CPM: Activities Immediate Time Estimates (Days) Predecessors Optimistic (a) Most Likely (m) Pessimistic (b) A-135

The following represents a project that should be scheduled using CPM:

Activities Immediate Time Estimates (Days) Predecessors Optimistic (a) Most Likely (m) Pessimistic (b)

A-135 B-123 CA123 DA234 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5

  1. (1) Draw the precedence diagram. (Use the first decimal place for the expected duration and use the second decimal place for the variance.)

  2. (2) What is the probability that the project can be completed in 16 days or less?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!