Question: Question 4 10 pts The following represents a project that should be scheduled using CPM with 3 time estimates: Time in weeks Activity Predecessors Optimistic

Question 4 10 pts The following represents a

Question 4 10 pts The following represents a project that should be scheduled using CPM with 3 time estimates: Time in weeks Activity Predecessors Optimistic Most Probable Pessimistic 4 6 0 + + I CF 2 What is the probability that the project will exceed 30 weeks? 15.39% 34.16% 27.67% 28.67%