Question: The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B A D A E B F C.D G DE

The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B A D A E B F C.D G DE H F G TIMES (DAYS) a m b 1 2 6 1 2 9 2 2 11 1 8 9 1 2 3 3 4 11 1 3 11 2 3 11 b. What is the critical path? A-C-F-H B-E-G-H A-D-G-H A-D-F-H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 19 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.) Probability