Question: the following represents a project that should be scheduled using CPM: The following represents a project that should be scheduled using CPM: - IMMEDIATE ACTIVITY

the following represents a project that should be scheduled using CPM: the following represents a project that should be
the following represents a project that should be
The following represents a project that should be scheduled using CPM: - IMMEDIATE ACTIVITY PREDECESSORS A B A D E B F C,D G D, E H F,G TIMES (DAYS) a m b 1 2 6 1 2 3 2 5 11 1 2 12 1 2 3 1 3 5 1 3 11 2 3 11 b. What is the critical path? OB-E-G-H O A-C-F-H A-D-G-H A-D-F-H c. What is the expected project completion time? (Do not round intermediate Project completion time days