Question: The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) PREDECESSORS ACTIVITY a m b A 1 4 7 B 3
The following represents a project that should be scheduled using CPM:
IMMEDIATE TIMES (DAYS)
PREDECESSORS
ACTIVITY a m b
A 1 4 7
B 3 5 10
C A 2 5 8
D A 4 6 11
E B 1 2 3
F C,D 3 5 7
G D,E 1 2 6
H F,G 2 5 6
b. What is the critical path?
A-D-F-H
B-E-G-H
A-C-F-H
A-D-G-H
c. What is the expected project completion time?
Project completion time __________ days
d. What is the probability of completing this project within 22 days?
Probability _________