Question: The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A 1 2 6 B 1
| The following represents a project that should be scheduled using CPM: |
| TIMES (DAYS) | ||||
| ACTIVITY | IMMEDIATE PREDECESSORS | a | m | b |
| A | 1 | 2 | 6 | |
| B | 1 | 2 | 3 | |
| C | A | 2 | 5 | 11 |
| D | A | 1 | 2 | 12 |
| E | B | 1 | 2 | 3 |
| F | C, D | 1 | 3 | 5 |
| G | D, E | 1 | 3 | 11 |
| H | F, G | 2 | 3 | 11 |
| b. | What is the critical path? |
multiple choice
|
| c. | What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) |
| d. | What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.) |