Question: The following represents a project that should be scheduled using CPM: 13 IMMEDIATE ACTIVITY PREDECESSORS A B A E B F C,D G DE H

The following represents a project that should be
The following represents a project that should be
The following represents a project that should be scheduled using CPM: 13 IMMEDIATE ACTIVITY PREDECESSORS A B A E B F C,D G DE H F G TIMES (DAYS) a m b 1 4 7 2 6 1 1 4 3 4 4 6 5 9 wNN 9 b. What is the critical path? B-E-G-H A-C-F-H A-D-F-H A-D-G-H c. What is the expected project completion time? (Round your answer to 3 Project completion time days d. What is the probability of completing this project within 20 days? (Do notre Probability me? (Round your answer to 3 decimal places.) days -roject within 20 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!