Question: The following represents a project that should be scheduled using CPM: 11 IMMEDIATE ACTIVITY PREDECESSORS B C A D E B F C,D G DE

The following represents a project that should be scheduled using CPM: 11 IMMEDIATE ACTIVITY PREDECESSORS B C A D E B F C,D G DE H F,G TIMES (DAYS) a m b 1 1 4 4 5 6 3 7 1 2 9 1 6 8 1 2 12 3 10 . 3 10 NN b. What is the critical path? O A-C-F-H O B-E-G-H O A-D-G-H O A-D-F-H c. What is the expected project completion time? (Do not round intermedia Project completion time days d. What is the probability of completing this project within 19 days? (Round final answer to 4 decimal places.) Probability