Question: The following represents a project that should be scheduled using CPM: ACTIVITY ABCDEFGH IMMEDIATE PREDECESSORS AABCDE C, D D,E F,G b. What is the critical
The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D-F-H A-D-G-H B-E-G-H A-C-F-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places