Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS A (BCDEFGH O B-E-G-H A-D-G-H O A-D-F-H O A-C-F-H AABU b.

The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS A (BCDEFGH O B-E-G-H A-D-G-H O A-D-F-H O A-C-F-H AABU b. What is the critical path? C,D D, E F,G Project completion time Probability a 3312NPPTO TIMES (DAYS) EMNNMA444 3 2 2 3 b days 1565 A WW35 c. What is the expected project completion time? Note: Do not round Intermediate calculations. Round your answer to 2 decimal places. 4 11 d. What is the probability of completing this project within 16 days? Note: Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round Intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.
 The following represents a project that should be scheduled using CPM:

The following represents a project that should be scheduled using CPM: b. What is the critical path? B-E-G-H A-D-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? Note: Do not round intermedlate calculations. Round your answer to 2 decimal ploces. d. What is the probability of compleung this project within 16 days? Note: Use Excel's NORMSDIST0 function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round " z " value to 2 decimal places and final answer to 4 decimal places

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!