Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS A (BCDEFGH O B-E-G-H A-D-G-H O A-D-F-H O A-C-F-H AABU b.
The following represents a project that should be scheduled using CPM: b. What is the critical path? B-E-G-H A-D-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? Note: Do not round intermedlate calculations. Round your answer to 2 decimal ploces. d. What is the probability of compleung this project within 16 days? Note: Use Excel's NORMSDIST0 function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round " z " value to 2 decimal places and final answer to 4 decimal places
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
