Question: The following steps should be followed when adding resource input in Project Libre. Set the resource input Open Project Libre Open your project . Select
The following steps should be followed when adding resource input in Project Libre.
- Set the resource input
-
- Open Project Libre
- Open your project .
- Select Resources (Top tool bar)
- Add your resources
-
- Enter Resource Name
- Enter Resource Type
- Enter Rates
- Enter Base Calendar
-
- Enter the remaining resources using the same format as above.
- Set your resource information
-
- Select Resource
- Select information
- Enter Cost, Resource availability or additional information
- Go back to task to add your resources
-
- Go to task
- Click on Gantt
- Select the task
- Select assign resource
- Assign resources and unit percentages
- Add remaining resources
- Make sure to save your information
Step 2: Update Project Libre with Cost Inputs
The following steps should be followed when setting up your Course Project with Project Libre.
- Set the cost input
-
- Select a column
- Insert a column by right clicking
- Select cost
- Click ok
- Cost should be displayed from resource input
- Insert new column
- Select total slack
- Your total slack should be displayed
- Insert new column
- Select Free slack
- Your free slack should be displayed
- Select File
- Click Save Baseline
- Select Baseline one
- Select Entire project
- Click ok
- Go print preview
-
- Adjust your scale
- Or Fit to one page
- Select Printer setting to PDF
- Or save image in word and crop
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts