Question: The following table contains order - dependent setup times for three jobs. table [ [ , , Setup Time ( hours ) , Following

The following table contains order-dependent setup times for three jobs.
\table[[,,Setup Time (hours),Following Job's Setup Time (hours)],[,A,B,C],[,A,2.4,-,1.8,2.2],[Preceding Job,B,3.2,0.8,-,1.4],[,C,2.0,2.6,1.3,-]]
Click here for the Excel Data File
Which processing sequence will minimize the total setup time?
The sequence is
A-B-C
A-C-B
B-A-C
B-C-A
C-A-B
C-B-A