Question: The following table contains order - dependent setup times for three jobs. Following Job s Setup Time ( hours ) Initial Setup Time ( hours

The following table contains order-dependent setup times for three jobs.
Following Jobs Setup Time (hours)
Initial Setup Time (hours)
A
B
C
A
2.4
1.82.2
Preceding Job B
3.2
0.81.4
C
2.0
2.61.3
Which processing sequence will minimize the total setup time?
multiple choice
A-B-C
A-C-B
B-A-C
B-C-A
C-A-B
C-B-A