Question: The following table gives data on normal time and cost and crash time and cost for a project: table [ [ Activity , Normal,Crash

The following table gives data on normal time and cost and crash time and cost for a project:
\table[[Activity,Normal,Crash],[Time(days),Cost(Tk.),Time(days),Cost(Tk.)],[1-2,6,60,4,100],[1-3,4,60,2,200],[2-4,5,50,3,150],[2-5,3,45,1,65],[3-4,6,90,4,200],[4-6,8,80,4,300],[5-6,4,40,2,100],[6-7,3,45,2,80]]
(i) Draw the network for the project
(ii) Find the critical path
(iii) Determine minimum total time and corresponding cost.