The following table gives data on normal time and cost and crash time and cost of...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The following table gives data on normal time and cost and crash time and cost of project. Indirect cost is CAD 60 day Acitvity Name A 1-2 1-3 B 1-4 2-4 3-4 4-5 A) Draw the network diagram B) Find Critical path C) Crash the relevant activities symmetrically and determine the optimum project time and cost Marks 10 1 2345 6 7 8 C D E F 9 10 Normal Time 9 8 15 5 10 2 Normal Cost 640 500 400 100 200 100 Q2. Earned Value You're a subcontractor responsible for managing the installation of 10,000 feet of fence around an elementary school. You estimate the cost of fence installation to be $10 per foot. You estimate that your crew can install 500 feet of fence per week. After 12 weeks, you have 50% of the job complete and you have spent $45,000. Determine the value for each of the terms below: Marks 10 Crash Time 6 5 10 3 6 Term Budget at Completion (BAC) Planned Value (PV) Earned value (EV) Actual Cost (AC) Cost Variance (CV) Schedule Variance (SV) Cost Performance Index(CPI) Schedule Performance Index (SPI) Estimate at Completion Estimate to Complete 1 Crash Cost 700 575 550 120 260 140 Value The following table gives data on normal time and cost and crash time and cost of project. Indirect cost is CAD 60 day Acitvity Name A 1-2 1-3 B 1-4 2-4 3-4 4-5 A) Draw the network diagram B) Find Critical path C) Crash the relevant activities symmetrically and determine the optimum project time and cost Marks 10 1 2345 6 7 8 C D E F 9 10 Normal Time 9 8 15 5 10 2 Normal Cost 640 500 400 100 200 100 Q2. Earned Value You're a subcontractor responsible for managing the installation of 10,000 feet of fence around an elementary school. You estimate the cost of fence installation to be $10 per foot. You estimate that your crew can install 500 feet of fence per week. After 12 weeks, you have 50% of the job complete and you have spent $45,000. Determine the value for each of the terms below: Marks 10 Crash Time 6 5 10 3 6 Term Budget at Completion (BAC) Planned Value (PV) Earned value (EV) Actual Cost (AC) Cost Variance (CV) Schedule Variance (SV) Cost Performance Index(CPI) Schedule Performance Index (SPI) Estimate at Completion Estimate to Complete 1 Crash Cost 700 575 550 120 260 140 Value
Expert Answer:
Answer rating: 100% (QA)
A B C D E F A9 Activity ESEFLSLFTF 0 9 4 134 08080 A B C D E F 89 0 153 183 9 1413184 8 18... View the full answer
Related Book For
Applied Regression Analysis and Other Multivariable Methods
ISBN: 978-1285051086
5th edition
Authors: David G. Kleinbaum, Lawrence L. Kupper, Azhar Nizam, Eli S. Rosenberg
Posted Date:
Students also viewed these programming questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
The following table gives data on median salaries of full professors in statistics in research universities in the United States for the academic year 2007. a. Plot median salaries against years in...
-
The following table gives data on imports, GDP, and the Consumer Price Index (CPI) for the United States over the period 19752005. You are asked to consider the following model: ln Importst =...
-
In Problems 2628, find the value of each determinant. 21 5 0 26 -3 1 0
-
Assume that E. Guard Company uses a periodic inventory system and has these account balances: Purchases .............$400,000 Purchase Returns & Allowances .... $ 11,000 Purchase Discounts .........$...
-
Tozer Computers makes bulk purchases of small computers, stocks them in conveniently located warehouses, and ships them to its chain of retail stores. Tozer's balance sheet as of December 31, 2001,...
-
Is sustainable development a useful, practical perspective for business to adopt? If yes, how is it useful? Explain your view, giving reasons.
-
The initial proceeds per bond, the size of the issue, the initial maturity of the bond, and the years remaining to maturity are shown in the following table for a number of bonds. In each case the...
-
. Your company is opening a bank line of credit. The facility amount is $10MM with $3MM funded. The interest rate is 5% per year based on a three year commitment. The unused line fee is 0.2%, the...
-
Prove that each of the following formulas for (v. tv) defines an inner product on R3. Verify all the inner product axioms in careful detail: (a) V1W1 + 2V2w2 + 3v3w3 (b) 4v1w1 + 2 v1w2 + 2v2wi +4v2W2...
-
Ace company has determined that when they set their memory card price at Ksh800 per piece, the quantity demanded is 8000 per week. However, due to high competition by their competitors the demand...
-
Assume that the market equilibrium fee of physician consultation services is $150. Using demand-supply curve of physician services, show the changes in market equilibrium if all individuals in the...
-
Using {blog} as your base, create words with the following meanings: A small blog Someone addicted to blogging A blog that begs A math-oriented blog A book based on a blog A blog devoted to...
-
INCOME Everyday Flowers and Workshops Sales of Product Income Special Occasions Total Income COST OF GOODS SOLD Flower Purchases and Supplies Supplies and materials - COS Total Cost of Goods Sold...
-
Revenue $525,000 Sales Returns $13,900 Sales Discounts $12,400 Net Sales $498,700 Cost of Goods Sold $79,500 Gross Profit Gross Profit Margin % 84.06% Given the information above, what is the Gross...
-
If GDP was $3 trillion over a certain time period and aggregate expenditure was $2.8 trillion over the same time period, what should be expected to occur given that the country does not export?...
-
Can you please explain this question? It is based on New Zealand Agricultural Tax Jeff owns a six-hectare block near Christchurch. Jeff and his wife, Marie, bought the property three years ago with...
-
What is the mode?
-
In Example 27.3, the manufacturer of the drugs would like to determine how much more powerful the hypothesis-testing method would be if larger samples were collected. Plot the sample size versus the...
-
a. For the data from Problem 15 in Chapter 5, specify the orthogonal polynomial codings needed for coding PPM_TOLU linear, quadratic, and cubic terms. Repeat part (a) of Problem 12, but use the...
-
An experiment to evaluate the effects of certain variables on soil erosion was performed on 10-foot-square plots of sloped farmland subjected to 2 inches of artificial rain applied over a 20-minute...
-
Refer to exercise E2-28 of Chapter 2. Start from the trial balance and the posted T-accounts prepared at January 18, 2020. Later in January, the business completed these transactions: Requirements 1....
-
Refer to exercise E3-31. Requirements 1. After solving exercise E3-30, use the data in that exercise to prepare Yosaf Portraits Ltd.'s classified balance sheet at December 31, 2020. Use the report...
-
Satterfield Corporation reported the following current accounts at Deccmber 31, 2019 (amounts in thousands): During January 2020, Satterfield completed these selected transactions: - Sold services on...
Study smarter with the SolutionInn App