Question: The following table gives the processing times and due dates for five jobs which are to be processed on a machine. Assign the jobs according

 The following table gives the processing times and due dates for

The following table gives the processing times and due dates for five jobs which are to be processed on a machine. Assign the jobs according to the shortest processing time (SPT). Calculate the average flow time using a job order based on SPT. (Round your answer to 1 decimal place.) Answer is complete but not entirely correct