Question: The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the

The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the critical path?
Activity
Duration
Predecessor
A
B
2
4
C
D
E
F
6
3
7
2
End
Start
A, E
A
B, C Start
E
D, F
A-11
B-14
C-9
D-13