Question: The following table is data from a software engineering class project in the 1990s. Time period # of bugs found # of bugs removed #
The following table is data from a software engineering class project in the 1990s.
| Time period | # of bugs found | # of bugs removed | # of hours tested |
| Oct 21 Oct 31 | 13 | 3 | 6 |
| Nov 1 Nov 8 | 14 | 7 | 7 |
| Nov 9 Nov 16 | 8 | 3 | 3 |
| Nov 17 Nov 24 | 6 | 2 | 4 |
| Nov 25 Nov 30. | 4 | 4 | 1 |
Question: If they continue testing, how many more defects would they find? What other information would you need? Write any assumptions or preconditions as appropriate. Does the hour for testing seem reasonable at the end of the project? Why or why not?