Question: The following table lists the activity time estimates ( in weeks ) for each activity. Activity Optimistic Most Probable Pessimistic 5 6 B 2 .
The following table lists the activity time estimates in weeks for each activity.
Activity
Optimistic
Most Probable
Pessimistic
B
D
F
G
H
Based only on the critical path, what is the estimated probability that the project will be completed with frame? Round your answers to four decimal places.
a Within weeks?
b
Within weeks?
c
Within weeks?