Question: Critical Path for Blue Lagoon Pools. The following table lists the activity time es - timates ( in days ) for Blue Lagoon's swimming pool

Critical Path for Blue Lagoon Pools. The following table lists the activity time es-timates (in days) for Blue Lagoon's swimming pool installation project in Problem 11. LO 2,3,4 Activity A B C D E F G H I Optimistic 325721563 Most Probable 5 46942884 Pessimistic 6 67 1063 10105 a. What are the critical activities? b. What is the expected time to complete the project? c. Based only on the critical path, what is the estimated probability that the project can be completed in 25 or fewer days?