Question: The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F

The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
Item End B C D E F G H
LT (week)13331111
Amount on hand 07122283260
Click here for the Excel Data File
Note: If you click the Hint link on the left you can watch a walk-through of the problem using different numbers.
a. If 23 units of the end item are to be assembled, how many additional units of E are needed? (Hint: It will be easier to work through this if you redraw the BOM and add in the information on leadtime and how many units of each are in stock.)
b. An order for the end item is scheduled to be shipped at the start of week 17. What is the latest week that the order can be started and still be ready to ship on time? (Hint: Find the longest leadtime path in the product (also called cumulative leadtime) and then subtract it from 17.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!