Question: The following table lists the components needed to assemble an end item, lead times, and quantities on hand. a. If 20 units of the end
The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
.png)
a. If 20 units of the end item are to be assembled, how many additional units of E are needed?
b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time?
End BCDEF G H Item LT (wk) Amount on hand 0 10 10 25 12 30 5 0 End Item B (2) D (3) E (2) F (3) G (2) E (2) H (4) E (2)
Step by Step Solution
3.38 Rating (154 Votes )
There are 3 Steps involved in it
Given We have the following information Item End B C D E F G H LT wk 1 2 3 3 1 2 1 2 Amount on hand ... View full answer