Question: The following table lists the components needed to assemble an end item, lead times, and quantities on hand. a. If 20 units of the end

The following table lists the components needed to assemble an end item, lead times, and quantities on hand.


The following table lists the components needed to assemble an


a. If 20 units of the end item are to be assembled, how many additional units of E are needed?
b. An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time?

End BCDEF G H Item LT (wk) Amount on hand 0 10 10 25 12 30 5 0 End Item B (2) D (3) E (2) F (3) G (2) E (2) H (4) E (2)

Step by Step Solution

3.38 Rating (154 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Given We have the following information Item End B C D E F G H LT wk 1 2 3 3 1 2 1 2 Amount on hand ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

372-B-M-L-O-M (3283).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!