Question: The following table lists the components needed to assemble an end item X , quantities on - hand, and lead times. Also, there is a

The following table lists the components needed to assemble an end item X, quantities on-hand, and lead times. Also, there is a scheduled receipt of 5 units of subassembly A in week 2 and lot-for-lot ordering is used for all items. If 12 units of the end item are needed at the beginning of week 6, prepare a material requirements plan for E.
Item X A B C D E F
Quantity on-hand 0162404004
Lead time (weeks)1211211
X
B (3) A
D (4) E E (2) C
E (5) F (2)
 The following table lists the components needed to assemble an end