Question: The following table lists the components needed to assemble an end item, including quantities on hand. Lead times in werks) to order, receive and assemble

The following table lists the components needed
The following table lists the components needed to assemble an end item, including quantities on hand. Lead times in werks) to order, receive and assemble are also provided (This question uses the same numbers as the previous question) Item Amount on Hand Direct Components Lead Time End 5 E12). F(1) 2 E 25 Al2), B(1) 2 35 A[4), C(2), D[3) 2 350 4 55 3 A B c D 95 2 105 3 1 How many of component A are needed to produce 100 units of the End item? 210 O 220 O 230 0 260