Question: The following table lists the components needed to assemble an end Item, lead times, and quantities on hand. Item LT (week) Amount on hand End
The following table lists the components needed to assemble an end Item, lead times, and quantities on hand. Item LT (week) Amount on hand End 2 0 B 2 8 2 11 D 2 23 E 2 9 F 2 28 G 2 6 INO Click here for the Excel Data File End Item B021 a) E (2) 2) E (2) E12 F a. If 22 units of the end Item are to be assembled, how many additional units of E are needed? (Mine You don't need to develop an MRP plan to determine this.) Additional units b. An order for the end item is scheduled to be shipped at the start of week 14. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either) The latest week