Question: The following table outlines project Y: Activity Preceding Time (in days) Max days to crash Total Crushing Cost (for maximum days) A -- 8 1
The following table outlines project Y:
| Activity | Preceding | Time (in days) | Max days to crash | Total Crushing Cost (for maximum days) |
| A | -- | 8 | 1 | 200 |
| B | -- | 3 | 1 | 50 |
| C | A | 7 | 2 | 100 |
| D | A, B | 3 | - | 0 |
| E | C | 6 | 1 | 75 |
| F | D | 3 | - | 0 |
| G | D | 2 | - | 0 |
| H | G | 3 | 1 | 20 |
Q1. Identify the critical path and calculate the project duration
Q2. What is the cost of crushing the project by 3 days