Question: The following table outlines project Y: Activity Preceding Time (in days) Max days to crash Total Crushing Cost (for maximum days) A -- 8 1

The following table outlines project Y:

Activity

Preceding

Time (in days)

Max days to crash

Total Crushing Cost (for maximum days)

A

--

8

1

200

B

--

3

1

50

C

A

7

2

100

D

A, B

3

-

0

E

C

6

1

75

F

D

3

-

0

G

D

2

-

0

H

G

3

1

20

Q1. Identify the critical path and calculate the project duration

Q2. What is the cost of crushing the project by 3 days