Question: The following table provides the information necessary to construct a project network and project crash data: Find: a)Present (normal) critical path, b) Normal critical path
The following table provides the information necessary to construct a project network and project crash data: Find: a)Present (normal) critical path, b) Normal critical path time, c) Crash critical path, d)Crash critical time, e) Normal cost, f) Minimum crashed project cost

20 Activity Activity Time (weeks) Activity Predecessor Normal Crash 8 24 20 14 10 11 Activity Cost ($) Normal Crash 1,000 1,480 1,200 700 1,190 500 820 550 730 1,400 2 3 7 6 4 1 on w on
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
