Question: The following table provides the information necessary to construct a project network and project crash data: Find: a)Present (normal) critical path, b) Normal critical path

The following table provides the information necessary to construct a project network and project crash data: Find: a)Present (normal) critical path, b) Normal critical path time, c) Crash critical path, d)Crash critical time, e) Normal cost, f) Minimum crashed project cost

The following table provides the information

20 Activity Activity Time (weeks) Activity Predecessor Normal Crash 8 24 20 14 10 11 Activity Cost ($) Normal Crash 1,000 1,480 1,200 700 1,190 500 820 550 730 1,400 2 3 7 6 4 1 on w on