Question: show steps please Consider the following three estimates for the duration of an activity: Optimistic (tO) =4 weeks Most likely (tM)=5 weeks Pessimistic (tP)=9 weeks

show steps please
Consider the following three estimates for the duration of an activity: Optimistic (tO) =4 weeks Most likely (tM)=5 weeks Pessimistic (tP)=9 weeks Using the beta distribution and the three-point estimating approach, the calculated Expected activity duration (tE) is: 4.5 weeks. 4.0 weeks. 5.5 weeks. 6.5 weeks. QUESTION 7 Consider the following information about the duration of an activity: Calculated expected (tE)=5 weeks Optimistic (tO) =4 weeks Pessimistic (tP)=8 weeks Using the beta distribution and the three-point estimating approach, the Most likely (tM) activity duration is: 6.0 weeks. 4.5 weeks. 4.0 weeks. 5.0 weeks